Design Phase
Fire House #5 and #6

Design Phase

Achievements and next steps

ACHIEVEMENTS:
CMAR Preconstruction Negotiation
100% Schematic Design complete
100% Design Documents 20-Aug
Storm Shelter Proposal Recieved

NEXT STEPS:
Terracon Engineering Scope and Contract
100% DD Review by City
Initial Estimates (Mid-Sept)
50% Construction Documents 01-Oct
100% CD’s Complete 29-Nov
100% CD’s City Review (6 weeks)