Fire House #5 and #6

Construction Progress

Achievements and next steps

ACHIEVEMENTS:
Contract Negotiations
City Council Approval 22-JUL
Permitting Finalized
SWPPP Permit Complete
Temporary Fire Station Trailer Delivered
Obtain Construction Permit
Kick-Off Meeting 01-AUG
Issue Notice to Proceed 01-AUG
CORE Construction Mobilization 04-AUG
Tree Protection, Clearing and Grubbing

NEXT STEPS:
Temp Station Submittals 11-AUG
Procure Sprung Structure
Sprung Structure August –November
Temp Station Flex base
Temp Station Trailer MEP
Sprung Foundation
Install Sprung Structure
Install OH Doors
Moisture Conditioning Building Pad 08-SEP
Start Sanitary Sewer Install 22-SEP
Start Storm Sewer Install 22-SEP
Pier Survey Followed by Drilling 23-SEP