ACHIEVEMENTS:
Received Bids 25-MAR
Pre-Bid Meeting 12-MAR
Advertise for Bids 5-MAR
Modular IT Equipment Plan
CORE Bid Package Submitted to City Purchasing for Review
Terracon Engineering Services Scope and Contract Approved by City Council
100% Construction Documents Submitted for Permitting
FF&E Budget Development (DFS5&Modular)
Art Package Submitted for Bids

NEXT STEPS:
Sprung App Bay and Trailer Purchase and Transportation
Finalize Utilities for Temp Station
Plan Permit Review (In Progress)
Art Bids Due 31-MAR
GMP to City for Review 15-APR
GMP to Council 5-May
Construction (June)