August 2026 Status Update and Lookahead to upcoming work
• Del Dr: Lime treated subgrade complete, asphalt scheduled for week of Aug. 4th.
• Water line tie-in at Del & Donna to be 8/18/2026
• Donna Rd: Prepping for sod.
• Jupiter Dr: Demolition completed, first mix of lime was on 7/28/2026.
• Neptune Dr: Asphalt scheduled for July 31st. Backfilling & placing topsoil, prepping for sod.
• Pershing Dr: Concrete crews resumed work on Pershing Drive on 7/28/2026, forming and prepping for sidewalk construction.
• Selene Dr: Backfilling to start.
• Riney Rd: Sanitary Sewer installation complete, roadway demo to start next.
• Royal Acres: Water main and services installation to be completed & hydrostatic test, 7/31/2026. Chlorination week of 8/3/2026. Water main tie-in at Royal Acres & Sherman scheduled for 8/6/2026.
• Redstone Rd - South Half (hercules to Atlas) - Earthwork crews working on backfill & topsoil getting it prepped for sod. North Half (Atlas to Neptune)– Sundt continues sewer installation which will be completed by Tuesday, August 4th.
Upcoming Sod Installation
• Donna Rd
• Redstone Rd (South)
Punch List Progress, Sundt continues to hold weekly internal punch list meetings to ensure all outstanding items are being addressed.
• Sheraton Rd & Huntington Dr: Working through City's Street punch list. Utility punch list walk with City of Denton took place 7/30/2026.
• Sunnydale Ln: Sundt's internal punch list corrections are ongoing.
• Apollo Dr & Titan Tr: Sundt's Internal punch list corrections are ongoing.
• Wellington Dr & Buckingham Dr: Sundt's Internal punch list corrections are ongoing.
• Northridge: Utility Punch list corrections are ongoing – one outstanding item remaining (bolts are on order for the one item). Street punch list closed out.