Neighborhood 1B
The 2019 Bond Neighborhood 1B project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided at the bottom for all streets that will be part of the Neighborhood 1B project as well as the breakdown of the phases. Street reconstruction will include new curb and gutter, sidewalk and pedestrian improvements, reconstructed asphalt roadways and upgrading select water, and wastewater facilities.
Estimated Budget: $31 Million
Sponsoring Department:
Capital Projects
Water Distribution
Wastewater Collections
Streets
Project Location: Various Street Locations
Additional updates provided by Sundt Construction can be found here.
Project Timeline Q4 2023 - Q4 2026
Initiation Phase
CMAR & Design Firm Selection and Design Phase
NTP & Construction Phase
Stay Informed
Get notified on upcoming engagements and the latest project related news.

Project Updates
NBHD 1B
July 2026 Update & Lookahead
June 2026 Update and Lookahead - 2
June 2026 Update and Lookahead
Status of work since last update
May 2026 Update and Lookahead
March 2026 Update and Lookahead
March Update and Lookahead
March Update and Lookahead
February Update and Lookahead
February Update and Lookahead
January Update and Lookahead
January Update and Lookahead
December Update and Lookahead
December Update and Lookahead
November Update and Lookahead
New Update
October Update & Lookahead
Update as of 10/24/2025
September Update & Lookahead
Update as of 9/18/2025
August Update & Lookahead
New Update as of 08-20-2025
July Update
Utility improvements continue along various streets as well as road reconstruction on several street segments.
June Update
The contractor continues to make progress with utility installation along various segments of the project.
May Update
With this project officially underway, the contractor has begun the removal of existing asphalt paving and curb and gutter along several segments.
April Update
City staff conducted a virtual community meeting on Aril 3rd.
March Update
Neighborhood 1B construction contract with Sundt Construction will go to City Council for approval on March 4, 2025.