Visit Denton, TX Homepage
Construction crew paving road

Neighborhood 1B

The 2019 Bond Neighborhood 1B project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided at the bottom for all streets that will be part of the Neighborhood 1B project as well as the breakdown of the phases. Street reconstruction will include new curb and gutter, sidewalk and pedestrian improvements, reconstructed asphalt roadways and upgrading select water, and wastewater facilities.



Estimated Budget: $31 Million

Sponsoring Department:

Capital Projects
Water Distribution
Wastewater Collections
Streets

Project Location: Various Street Locations

Additional updates provided by Sundt Construction can be found here.

Project Timeline Q4 2023 - Q4 2026

Initiation Phase

1 year

CMAR & Design Firm Selection and Design Phase

2 years

NTP & Construction Phase

1 1/2 years
Photo of project map

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Photo of Dante Hale
Dante Hale, PMP
Construction Projects Manager

Project Updates

19 items

NBHD 1B

Posted:
View Update

July 2026 Update & Lookahead

Posted:
View Update

June 2026 Update and Lookahead - 2

Posted:
View Update

June 2026 Update and Lookahead

Status of work since last update

Posted:
View Update

May 2026 Update and Lookahead

Posted:
View Update

March 2026 Update and Lookahead

Posted:
View Update

March Update and Lookahead

March Update and Lookahead

Posted:
View Update

February Update and Lookahead

February Update and Lookahead

Posted:
View Update

January Update and Lookahead

January Update and Lookahead

Posted:
View Update

December Update and Lookahead

December Update and Lookahead

Posted:
View Update

November Update and Lookahead

New Update

Posted:
View Update

October Update & Lookahead

Update as of 10/24/2025

Posted:
View Update

September Update & Lookahead

Update as of 9/18/2025

Posted:
View Update

August Update & Lookahead

New Update as of 08-20-2025

Posted:
View Update

July Update

Utility improvements continue along various streets as well as road reconstruction on several street segments.

Posted:
View Update

June Update

The contractor continues to make progress with utility installation along various segments of the project.

Posted:
View Update

May Update

With this project officially underway, the contractor has begun the removal of existing asphalt paving and curb and gutter along several segments.

Posted:
View Update

April Update

City staff conducted a virtual community meeting on Aril 3rd.

Posted:
View Update

March Update

Neighborhood 1B construction contract with Sundt Construction will go to City Council for approval on March 4, 2025.

Posted:
View Update