Update 9/18/25
NBHD 1B
Cactus Circle: Yucca Dr. to Cul-de-sac – Curb & gutter started. Driveways to follow.
Huisache Street: Aspen Dr. to Yucca Dr. – Flatwork complete. HMA tentative for next week. Curb and gutter for Aspen this week.
Northridge Street: Hinkle Dr. to Bolivar St. – Sanitary sewer (SS) underway. Crew is finishing services on Line B (Mesquite to Carroll). Main continued on Line A (Mesquite to Hinkle).
Sunnydale Lane: Kings Row to Sun Valley Dr. – SS main complete. Roadway milled today. Lime scheduled Monday 9/22 with asphalt and flatwork to follow.
Yellowstone Place: Hercules Lane to Juno Ln. – Curb & gutter starting next week.
Sheraton Road: Imperial Dr. to Sun Valley Dr. – Crew continuing to work through storm drain and DIP. Sewer main continuing.
Pershing Drive: Atlas Dr. to Stuart Rd. – SS main construction underway. Excavation in rock.
Titan Trail – Utilities potholed. Crew will mobilize in the next couple weeks.
Camelot Street: Hercules Ln. to Stuart Rd – Roadway work complete. Awaiting favorable weather to place sod. No current presence on the road.
Juno Lane: Atlas Dr. to Stuart Rd – Roadway complete. Striping and Sod to follow. No current presence on the road
Redstone Road: Hercules Ln. End – SS delayed for Atmos gas line conflicts. Sundt demobilizing this week 8/20.
Updated as of 09-12-2025
Juno Lane: Atlas Dr. to Stuart Rd. – Concrete construction complete. Final HMA lift scheduled for tomorrow 9/5.
Cactus Circle: Yucca Dr. to Cul-de-sac – First Lift HMA today 9/4. Concrete Flatworks to follow.
Huisache Street: Aspen Dr. to Yucca Dr. – Concrete curb & gutter complete, driveways started.
Northridge Street: Hinkle Dr. to Bolivar St. – Sanitary sewer (SS) underway. Crew is installing services on Line B (Mesquite to Carroll). Main started on Line A (Mesquite to Hinkle).
Selene Drive: Stuart Rd. to End – Trench line to be backfilled with base. Work will resume with tie in for Apollo, tentative early October.
Sunnydale Lane: Kings Row to Sun Valley Dr. – SS main completing this week. Remaining services to follow. Estimated completion of main and services 9/10.
Yellowstone Place: Hercules Lane to Juno Ln. – HMA first lift placed. Roadway prepared for concrete works to start following Huisache St.
Sheraton Road: Imperial Dr. to Sun Valley Dr. – SS Main started 9/2.
Pershing Drive: Atlas Dr. to Stuart Rd. – Revised drawings received. SS main started 9/2.
Camelot Street: Hercules Ln. to Stuart Rd – Roadway work complete. Awaiting favorable weather to place sod. No current presence on the road.
Redstone Road: Hercules Ln. End – SS delayed for Atmos gas line conflicts. Sundt demobilized 8/20.