Project

Work Commencing on Russell Newman, Teasley Ln & Shady Oaks Dr

Mill Overlay Package

Work will begin on Russell Newman Blvd from N Loop 288 to N Mayhill Rd on 7/8/2026 with anticipated completion by 7/15/2026*.

Work will begin on Teasley Ln & Shady Oaks Dr from I-35 Frontage Road to Colorado Blvd on 7/13/2026* with anticipated completion by 7/31/2026*.

Scope of work includes:
-3" mill and overlay of the street
-Concrete flatwork including limited driveways, sidewalk and curb and gutter.

Traffic control will be in place with rolling lane closures.

*Pending weather and any unforseen circumstances.