Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements

Lots of Work Underway

Our team has made substantial progress on various aspects of the project.

Our team has made substantial progress on various aspects of the project. The chemical containment pit's foundation, walls, and piers are now complete. The ground storage tank foundation is ready for the next phase, with excavation, backfilling, and mud slab pouring finished. Additionally, hundreds of feet of duct bank have been installed for the electrical system. As we move into next week, we'll begin drilling piers for the Variable Frequency Drive building.

Photo of chemical containment pit's foundation