Construction Progress
Project

Construction Progress

Fire House #5 and #6

FS #6
ACHIEVEMENTS:
 Steel work completed over the Bays and House
 Framers mobilized
 Building Dry-In
 Box walk with the City team
NEXT STEPS:
 Install Metal Roof over Bay area
 Complete Duct Work Install
 Complete Drywall installation on House Side

FS #5
ACHIEVEMENTS:
 Building demoed
 Coordination with Bonnie Brae project connections
 All piers drilled – with only 10 total piers cased
 Water Shutdown
NEXT STEPS:
 Pouring Grade Beams
 Installation of underground utilities
 Slab on Void Pour
 Steel fully delivered on site