Construction Progress
ACHIEVEMENTS: Steel work completed over the Bays and House Framers mobilized Building Dry-In Box walk with the City team Nearing Completion of Exterior CMU NEXT STEPS: Install Metal Roof over Bay area Complete Duct Work Install Complete Drywall installation on House Side Paint House Side Interior Complete Electrical Rough In NEXT STEPS: Install Metal Roof over Bay area Complete Duct Work Install Complete Drywall installation on House Side Paint House Side Interior Complete Electrical Rough In
Fire House #5 and #6