Construction Progress
Fire Station #6: ACHIEVEMENTS: Steel work completed over the Bays and House Framers mobilized Building Dry-In Box walk with the City team NEXT STEPS: Install Metal Roof over Bay area Complete Duct Work Install Complete Drywall installation on House Side Fire Station #5 ACHIEVEMENTS: Building Slab Poured Complete Storm Shelter CMU Fire Lane Poured NEXT STEPS: Complete Install Load Bearing CMU Walls Commence Structural Steel Complete Underground Utilities