Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Bernard North (Chestnut / Hickory) – Tie-ins scheduled.
Earthwork/Flatwork:
- Alice (Panhandle / Crescent) – Continue driveways and miscellaneous concrete followed by backfilling and sod.
- Cordell Change Order – Removals complete and concrete work to begin.
- Denton St. (Hickory / Congress E and Oak) – ATMOS delay.
- Egan (East - Anna / Bolivar) – Pending placement of sod.
- Emery and Fulton – Pending final lift of asphalt followed by striping and signage.
- Normal (Scripture / Oak) – Pending placement of sod and striping.
- Panhandle (Fulton / Denton) – Pending sod placement at driveways and final lift of asphalt.
- Parkway (Denton / Carroll) – Pending sod placement and final lift of asphalt followed by striping and signage.
- Ponder (Grace Temple / Oak) – Pending final lift of asphalt followed by striping and signage.
- Prairie – Pending striping at Bernard crosswalk.
- Scripture West (Malone / Bryan) – Continue rough grading followed by lime treated subgrade.
- Scripture East (Bryan / Ponder) – Continue rough grading followed by lime treated subgrade.
- Sunset (Carroll / Bolivar) – Pending final lift of asphalt followed by striping and signage.