
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Bernard North (Chestnut / Hickory) – Pending installation of storm drain and inlets.
Earthwork/Flatwork:
- Alice (Panhandle / Crescent) – Continue miscellaneous concrete followed by backfilling and sod.
- Cordell Change Order – Continue forming concrete.
- Denton St. (Congress / Oak) – Demo flume followed by concrete placement of sidewalk and ramps.
- Emery and Fulton – Pending traffic control removals.
- Panhandle (Fulton / Denton) – Pending placement of sod at driveways and traffic control removals.
- Parkway (Denton / Carroll) – Pending placement of sod.
- Ponder (Grace Temple / Oak) – Pending placement of sod.
- Scripture West (Malone / Ponder) – Pending placement of lime and remix followed by fine grading and first lift of asphalt.
- Sunset (Carroll / Bolivar) – Pending removals of traffic control.
Contact Us
Stay Informed
Stay in the loop with all the latest updates on upcoming engagements and project news by signing up for notifications.