Denton, TX
Construction crew working in ground

Westgate Drive Improvement Project

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Initiation and Planning & Design phases are complete
Currently in the Advertise, Bid, & Award phase

Project Timeline: 2021 - 2026

Estimated Budget: Reviewing Bids

Sponsoring Department: Capital Projects/Engineering

Funding Source: 2014 Bond Program

Project Location: Westgate Drive

Contact Information:
Multi-phase projects may require different project managers. Below are the current project managers and the phase they manage.

Upcoming Virtual Community Meeting Link:

Westgate Drive Virtual Community Link

Construction crew laying concrete

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Jesus Perez, Dante Hale
Construction Projects Manager CIP.Admin@cityofdenton.com

Project Updates

37 items

April Update

View Update

Westgate Dr Phase 1 March Update

Westgate Dr Phase 1 March Update

View Update

Phase 2 - Right-of-way Acquisition is on hold.

Right-of-way Acquisition is on hold until further notice

View Update

February Update

February Update

View Update

Phase 1 December Update

Phase 1 December Update

View Update

Phase 1 November Update

Boom! The waterline is completed and tied into the existing system.

View Update

Phase 1 October Update

And just like that, we have installed the majority of the drainage system! We have also begun installing the proposed waterline near the high school.

View Update

Phase 1 September Update

We are well underway!

View Update

Phase 1 August Update

It's official... This project is underway!

View Update

Phase 1 July Update

This contract was awarded to McMahon Contracting LLP on June 17th, 2025.

View Update

Phase 2 - Right-of-way Acquisition is on hold

Right-of-way acquisition for Phase 2 is on hold until further notice.

View Update

Phase 2 - Project Limit Reminder

The Westgate Drive Improvement Project has been split into two phases.

View Update

Phase 1 April Update

Phase 1 of this project is currently open for bidding, with the submission deadline set for April 9th.

View Update

Phase 2 - Right-of-way Acquisition

Right-of-way acquisition continues for Westgate Drive Phase 2 Project.

View Update

New project limits - Westgate Drive Phase 2 Improvement Project

Westgate Drive Phase 2 Improvement Project limits are (1) from Barrow Drive to Windsor Drive.and (2) Windsor Drive from I35 access road to Westgate Drive.

View Update

The East/West Westgate Drive will be first to be constructed.

City Staff has decided to construct the East/West Westgate Drive as the first phase of construction.

View Update

Right-of-way Acquisition continues

The City of Denton continues forward with the preparation of the Surveyor's Exhibits needed for North/South Westgate Drive and Windsor Drive.

View Update

City has purchased 0.3 mitigation credit.

City has purchased 0.3 mitigation credit for the upcoming construction project within the recognized wetlands.

View Update

United States Army Corps of Engineers issues Permit Authorization Letter

The City of Denton has received the authorization letter to move forward with construction activities.

View Update

100% Pre-Final Plan Set being reviewed by City.

After receiving the plans in late June, the City is reviewing the 100% Pre-Final Plans for any final changes.

View Update

Consultant Engineer plans to submit 100% Plan Set in late June 2024

The Consultant Engineer has compiled all of the City Staff comments and plans to submit the 100% Plan Set to the City in late June 2024.

View Update

Virtual Community Meeting

The City of Denton will hold a Community Meeting on Wednesday, June 12 at 6:00 p.m. regarding the roadway construction of the Westgate Drive Improvement Project.

View Update

The 90% Plan Set review continues at the City!

The 90% Plan Set submitted by Halff Associates continues to be reviewed by both external and internal stakeholders.

View Update

90% Plan Set submitted to the City.

Halff has submitted the prepared 90% Plan Set for City review.

View Update

Halff Associates continues to work on permanent and temporary construction easement documents.

Halff Associates continues to work on the permanent and temporary construction easements that will be needed for the construction project.

View Update

ROW acquisitions to begin soon.

The City of Denton Real Estate Department and the Consultant Engineer have begun the process of preparing documents for right-of-way acquisitions.

View Update

Completing plan revisions

The Consultant Engineer is completing the recommended changes to the 60% Plan Set.

View Update

60 percent plan set is complete!

The Consultant Engineer has submitted to the City the 60% Plan Set for its review.

View Update

30 Percent Plan Schematic is complete.

The 30% Plan Schematic has been completed by the Consultant Engineer.

View Update

Design Survey is Complete.

The Design Consultant, Halff, has completed their design survey.

View Update

Westgate Drive

Halff Associates, Inc. have started the design plans.

View Update

Choosing the Consultant Engineer for Design

The Engineering/Capital Improvement Project Department have completed their review of the "request for qualifications" process from a list of prequalified engineering firms

View Update

Westgate Project Scope Update

During the Tuesday, August 10 Work Session, City staff presented City Council with an overview of the traffic study that was conducted, additional analysis, and requested feedback from the Council on the final scope of the project.

View Update

Westgate Improvements Project Update

Based on feedback received at the June 8 City Council Work Session Presentation on the scope of the Westgate Reconstruction Project

View Update

Thursday, May 20 Virtual Community Meeting Replay

On Thursday, May 20, City staff hosted a virtual community meeting regarding the Westgate Improvements project.View the community meeting replay below.

View Update

Virtual Community Meeting Thursday, May 20

The City of Denton will hold a Virtual Community Meeting on Thursday, May 20, regarding street and utility improvements in your area as part of the Westgate Capital Improvement Project (CIP).

View Update

Westgate Improvements Project Update

Staff is considering options to ensure necessary connectivity for residents of the Westglen neighborhood during construction and access concerns associated with the opening of the new Denton High School as well as other development in the area.

View Update