Visit Denton, TX Homepage
Photo of street with orange cones and green landscape with a sidewalk next to the street

Westgate Drive Improvement Project

The Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project was divided into two phases, with Phase 1 having been completed in April of 2026. This phased approach allowed us to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 Status - Completed April 2026

Phase 1 Scope - included construction of wet utilities, streetlights, pedestrian improvements, and steel reinforced concrete roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 Status - Currently in design phase at 99% with easement and ROW acquisition underway. Construction timing will be dependent on the Denton County Bond issuance and the City CIP.

Phase 2 Scope - Westgate will be widened from Windsor to Bronco Way in both directions with upgraded drainage, a reconstructed bridge featuring sidewalks, handrails, and five new 7 x 6 drainage boxes, along with additional improvements including new water and sanitary sewer utilities, streetlighting, pedestrian mobility upgrades, and expanded drainage infrastructure; additionally, Windsor will be widened to four continuous lanes from Westgate to the I‑35 frontage road.

*Following completion of Phase 1 of this project, it was observed that motorists who were traveling westbound along Bronco Way, were making a prohibited left turn to head southbound onto Westgate Drive. City of Denton Transportation Department is preparing to install a NO LEFT sign at this location to discourage this action. *

Contact Information:
Multi-phase projects may require different project managers. Below are the current project managers and the phase they manage.

Phase 1 - Dante Hale dante.hale@cityofdenton.com
Phase 2 - Jesus Perez jesus.perez@cityofdenton.com

Construction crew laying concrete

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Photograph of Dante Hale
Dante Hale, PMP
Phase 1 Project Manager
Photograph of Jesus Perez
Jesus Perez
Phase 2 Project Manager

Project Updates

38 items

Westgate Drive Phase 2 Right-of-way acquisition update

The Consultant Engineer has been directed to restart the right-of-way acquisition process along north-south Westgate Drive and Windsor Drive between the I35 access road and Westgate Drive.

View Update

Westgate Drive Improvement Construction is Complete!

We're done! All contracted work is completed.

View Update

Westgate Drive Phase 1 Update

Westgate Drive Phase 1 fencing and final walk-through update.

View Update

Westgate Drive Phase 2 - Right-of-way Acquisition is on hold.

Right-of-way Acquisition is on hold until further notice

View Update

Westgate Drive Improvement Installation Update

And just like that, we're done with all roadway and pedestrian paving throughout the entirety of the project!

View Update

Phase 1 December Update

Phase 1 December Update

View Update

Phase 1 November Update

Boom! The waterline is completed and tied into the existing system.

View Update

Phase 1 October Update

And just like that, we have installed the majority of the drainage system! We have also begun installing the proposed waterline near the high school.

View Update

Phase 1 September Update

We are well underway!

View Update

Phase 1 August Update

It's official... This project is underway!

View Update

Phase 1 July Update

This contract was awarded to McMahon Contracting LLP on June 17th, 2025.

View Update

Phase 2 - Right-of-way Acquisition is on hold

Right-of-way acquisition for Phase 2 is on hold until further notice.

View Update

Phase 2 - Project Limit Reminder

The Westgate Drive Improvement Project has been split into two phases.

View Update

Phase 1 April Update

Phase 1 of this project is currently open for bidding, with the submission deadline set for April 9th.

View Update

Phase 2 - Right-of-way Acquisition

Right-of-way acquisition continues for Westgate Drive Phase 2 Project.

View Update

New project limits - Westgate Drive Phase 2 Improvement Project

Westgate Drive Phase 2 Improvement Project limits are (1) from Barrow Drive to Windsor Drive.and (2) Windsor Drive from I35 access road to Westgate Drive.

View Update

The East/West Westgate Drive will be first to be constructed.

City Staff has decided to construct the East/West Westgate Drive as the first phase of construction.

View Update

Right-of-way Acquisition continues

The City of Denton continues forward with the preparation of the Surveyor's Exhibits needed for North/South Westgate Drive and Windsor Drive.

View Update

City has purchased 0.3 mitigation credit.

City has purchased 0.3 mitigation credit for the upcoming construction project within the recognized wetlands.

View Update

United States Army Corps of Engineers issues Permit Authorization Letter

The City of Denton has received the authorization letter to move forward with construction activities.

View Update

100% Pre-Final Plan Set being reviewed by City.

After receiving the plans in late June, the City is reviewing the 100% Pre-Final Plans for any final changes.

View Update

Consultant Engineer plans to submit 100% Plan Set in late June 2024

The Consultant Engineer has compiled all of the City Staff comments and plans to submit the 100% Plan Set to the City in late June 2024.

View Update

Virtual Community Meeting

The City of Denton will hold a Community Meeting on Wednesday, June 12 at 6:00 p.m. regarding the roadway construction of the Westgate Drive Improvement Project.

View Update

The 90% Plan Set review continues at the City!

The 90% Plan Set submitted by Halff Associates continues to be reviewed by both external and internal stakeholders.

View Update

90% Plan Set submitted to the City.

Halff has submitted the prepared 90% Plan Set for City review.

View Update

Halff Associates continues to work on permanent and temporary construction easement documents.

Halff Associates continues to work on the permanent and temporary construction easements that will be needed for the construction project.

View Update

ROW acquisitions to begin soon.

The City of Denton Real Estate Department and the Consultant Engineer have begun the process of preparing documents for right-of-way acquisitions.

View Update

Completing plan revisions

The Consultant Engineer is completing the recommended changes to the 60% Plan Set.

View Update

60 percent plan set is complete!

The Consultant Engineer has submitted to the City the 60% Plan Set for its review.

View Update

30 Percent Plan Schematic is complete.

The 30% Plan Schematic has been completed by the Consultant Engineer.

View Update

Design Survey is Complete.

The Design Consultant, Halff, has completed their design survey.

View Update

Westgate Drive

Halff Associates, Inc. have started the design plans.

View Update

Choosing the Consultant Engineer for Design

The Engineering/Capital Improvement Project Department have completed their review of the "request for qualifications" process from a list of prequalified engineering firms

View Update

Westgate Project Scope Update

During the Tuesday, August 10 Work Session, City staff presented City Council with an overview of the traffic study that was conducted, additional analysis, and requested feedback from the Council on the final scope of the project.

View Update

Westgate Improvements Project Update

Based on feedback received at the June 8 City Council Work Session Presentation on the scope of the Westgate Reconstruction Project

View Update

Thursday, May 20 Virtual Community Meeting Replay

On Thursday, May 20, City staff hosted a virtual community meeting regarding the Westgate Improvements project.View the community meeting replay below.

View Update

Virtual Community Meeting Thursday, May 20

The City of Denton will hold a Virtual Community Meeting on Thursday, May 20, regarding street and utility improvements in your area as part of the Westgate Capital Improvement Project (CIP).

View Update

Westgate Improvements Project Update

Staff is considering options to ensure necessary connectivity for residents of the Westglen neighborhood during construction and access concerns associated with the opening of the new Denton High School as well as other development in the area.

View Update