Visit Denton, TX Homepage
Neighborhood 2&6 Streets with Active Construction
Project

Neighborhood 2&6 Streets with Active Construction

April update - 1

Neighborhood 2 & 6

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

Streets with active construction:

Utilities:

  • Bernard North (Chestnut / Hickory) – Tie-ins scheduled.

Earthwork/Flatwork:

  • Alice (Panhandle / Crescent) – Continue driveways and miscellaneous concrete followed by backfilling and sod.
  • Cordell Change Order – Removals complete and concrete work to begin.
  • Denton St. (Hickory / Congress E and Oak) – ATMOS delay.
  • Egan (East - Anna / Bolivar) – Pending placement of sod.
  • Emery and Fulton – Pending final lift of asphalt followed by striping and signage.
  • Normal (Scripture / Oak) – Pending placement of sod and striping.
  • Panhandle (Fulton / Denton) – Pending sod placement at driveways and final lift of asphalt.
  • Parkway (Denton / Carroll) – Pending sod placement and final lift of asphalt followed by striping and signage.
  • Ponder (Grace Temple / Oak) – Pending final lift of asphalt followed by striping and signage.
  • Prairie – Pending striping at Bernard crosswalk.
  • Scripture West (Malone / Bryan) – Continue rough grading followed by lime treated subgrade.
  • Scripture East (Bryan / Ponder) – Continue rough grading followed by lime treated subgrade.
  • Sunset (Carroll / Bolivar) – Pending final lift of asphalt followed by striping and signage.