Mill Overlay Package
Introduction
The City of Denton is committed to ensuring the safety, longevity, and quality of our roadways. As part of this initiative, we are undertaking a much-needed asphalt mill and overlay for select roadway segments. These improvements focus on enhancing pavement durability and driving conditions, targeting streets identified based on their condition, use, and subgrade integrity. By addressing these critical areas, we aim to extend the life of our infrastructure and maintain smooth, safe travel for all residents.To ensure the success and prioritization of this project, roadway segments were carefully selected using the Overall Condition Index (OCI) and thorough subgrade evaluations. This data-driven approach allows us to focus on preserving the structural health of our roads while addressing immediate surface needs. Your input is invaluable as we work together to make these improvements and shape the transportation infrastructure that benefits the entire Denton community.
The project scope includes the roadway segments listed below, which are expected to be completed within the specified timeframes, contingent on weather conditions.
- Teasley Lane: Between Interstate 35 and Dallas Dr.
July 14, 2026 - July 31, 2026 - Teasley Lane: Between Dallas Dr. and Shady Oaks Dr.
July 14, 2026 - July 31, 2026 - Shady Oaks Drive: Between Teasley Ln and Woodrow Lane.
July 14, 2026 - July 31, 2026 - Russell Newman Boulevard: Between Loop 288 and Mayhill Road.
July 8, 2026 - July 15, 2026 - Bonnie Brae Street: Between Scripture Street and University Drive.
July 8, 2026 - July 10, 2026
Design
Bid
Construction