Dudley Road Phases 3 & 4

Dudley Road Construction Project

About

We are thrilled to announce that we are nearing the completion of the Dudley Road construction project, and we are gearing up to begin phases 3 and 4 during the summer of 2024. The Dudley Road project has been a monumental undertaking, encompassing five total phases with a total construction cost exceeding $12 million. This transformative project spans nearly 3 miles in length, providing a significant improvement for our community's infrastructure and connectivity.

Project Overview:

Project Cost: The Dudley Road project's total construction cost exceeds $12 million, a substantial investment in our community's future.

Project Length: The construction project covers an approximate 3-mile stretch of Dudley Road, starting at Madison Pike and concluding at Dixie Highway.

Key Highlights:

Enhanced Safety: Our primary objective is to create safer roadways for all residents and travelers. Safety is at the forefront of our efforts.

Smoother Commutes: Bid farewell to those bumpy rides! The project includes extensive resurfacing to ensure your daily commutes are smoother and more enjoyable.

Long-term Asset Improvement: We are committed to maximizing the lifespan of our road system while minimizing maintenance costs. Innovative approaches, such as a flush curb design, have been implemented to save millions over the project's lifecycle.

Project Timeline:

Our dedicated engineering team has been diligently working with the Kentucky Highway Department to finalize construction documents for the past 6-9 months. In November, we submitted the final plans for review and approval. We are on track to secure approval by February 2024 and anticipate bidding the project in May 2024. Construction is scheduled to commence in late 2024 to early 2025, with an expected completion date in spring 2026. Regular updates on the project's progress will be provided to keep you informed about any potential traffic disruptions and milestones achieved.

Stay Informed:

To receive real-time updates and the latest information on the Dudley Road construction project, we invite you to sign up for our project updates or follow us on social media. This way, you can stay informed about important news and alerts as the project unfolds.

We acknowledge that road construction can be disruptive, and we deeply appreciate your patience and support throughout this endeavor. Together, we are shaping a brighter and more connected future for our community. Thank you for being an essential part of this transformative journey, and we eagerly anticipate witnessing the positive impact of the Dudley Road construction project on our community.

Dudley Road Plan Pic

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"This has been a tough project from start to finish. Designing a high volume traffic road that will last over time but limit traffic disruption has been extremely difficult. An even more difficult aspect was trying to budget for a $12 million project in a small city budget. But with the help of our elected officials, staff, engineers and great residents we are now entering the last two phases."
Brian Dehner
Brian Dehner
City Administrator

Construction Phases

Design and Engineering
Mid 2025
Stormwater Improvements
Fall 2023
Construction
2024-2026