Lilac Lane (BR-25-C1)
The purpose of this project is to improve the aging infrastructure of Lilac Lane as part of the overall City of Fargo improvement efforts.
Project Location
Lilac Lane from South Woodcrest Drive to North Woodcrest Drive and Willow Road from Lilac Lane to Woodcrest Drive
Full roadway reconstruction including:
- Water main replacement
- Water service replacement (to curb stop valve)
- Sanitary sewer main spot repairs
- Sanitary sewer service replacement (to behind the curb)
- Realignment of storm sewer pipe with new inlets and leads
- Driveway approaches (up to sidewalk)
- Sidewalk replacement
- Asphalt pavement
- New Street lighting
VIEW PROJECT INFO PDF
VIEW FULL SCREEN INTERACTIVE MAP
SPECIAL ASSESSMENTS
Part of this project is funded through special assessments. To check if a parcel has a special assessment, click the following link: www.fargoparcels.com
For more special assessment information click here.
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Project Phases
Phase 3: Lilac Ln from Willow Rd to North Woodcrest Dr
50 days
Phase 2: Intersection of Willow Rd and Lilac Ln, and Willow Rd from Lilac Ln to Woodcrest Dr
30 days
Phase 1: Lilac Ln from Willow Rd to South Woodscrest Dr
70 days
Project Updates
Important Dates
9
Apr 2025
Bid Date
19
May 2025
Phase 3 Start Date
12
Jun 2025
Phase 2 Start Date
31
Jul 2025
Phase 1 Start Date
13
Oct 2025