Main Street Improvements Project Update
The Main Street Improvements project is moving into its final stages! After a busy summer of construction, the long-awaited PUD vault lids are finally being delivered this week. Once installed and approved by PUD, the utlity companies will be able to complete the cutover from overhead to underground utilities.
Setting these vault lids will also allow the contractor to form and pour the remaining sidewalk sections. In the coming two weeks, crews will continue with sidewalk pours, final concrete, and landscaping.
We are excited to share that substantial completion is just around the corner, and we look forward to unveiling a renovated, more welcoming, and beautified downtown Main Street.
As always should you have any questions or concerns, please feel free to reach out to the City's Project Manager!