Project
NTMWD Project Update | April 10, 2026
Temporary transition from the northern staging area to the southern staging area complete
NTMWD Custer Road Water Main Replacement Project
Progress
- 5,100 of 9,100 feet of pipeline have been installed.
- Crews are continuing pipeline installation south towards Plano Parkway outside the northbound lane.
- Hydrostatic testing of the waterline from City of Plano Custer Pump Station to Plano Parkway passed.
- Permanent paving is being scheduled in coordination with trash pickup routes. Paving will begin at W 15th Street and Pitman Drive, and move south, currently scheduled for April 27.
Planned Traffic / Lane Impacts
Future traffic and/or lane impacts will continue to be coordinated with the City of Plano.
Neighborhood Impacts
- Cross streets and alleys between Westridge Drive and Westlake Drive will have temporary closures from 9 a.m. to 4 p.m., in sequence as crews move southward for permanent paving.
- Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses.
- Transition from the northern staging area to the southern staging area has been completed.
- Activities at the northern staging area will be reduced until the contractor comes back to perform tie-in and restoration, but may resume if inclement weather causes issues with access at the southern staging yard.
- Use of the staging areas is to last until project completion, which is currently targeted for October 26, 2026
Timeline / What’s Next
April-May 2026
- Atmos Energy initial phase of work is complete in the area, but will return after waterline installation is complete for permanent relocation of the gas line.
August 2026
- Anticipated shutdown of the City of Plano Custer Pump Station for final tie-in.
Later Phases (Date TBD)
- Testing/disinfection, permanent paving, and restoration of vegetation.
- Additional potholing will be performed along Carmel Drive requiring a street closure and a detour (timing will be shared once scheduled)
- A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle (timing will be shared once scheduled).
Contact Us
Email projects@ntmwd.com
Stay Informed
Stay in the loop with all the latest updates on upcoming engagements and project news by signing up for notifications.