NTMWD Project Update | October 23, 2026

Initial door hangers have been distributed to those who will have trash pickup impact.

NTMWD Custer Road Water Main Replacement Project

Progress

  • 9,050 of 9,100 feet of pipeline have been installed.
  • Crews completed pipeline installation under President George Bush Turnpike outside the northbound lane. Grouting and backfilling are complete within the City of Plano limits.
  • Permanent paving is being scheduled in coordination with trash pickup routes. Crews have paved through Pitman and Dolphin and have mobilized to Custer Road.

Planned Traffic / Lane Impacts*

Future traffic and/or lane impacts will continue to be coordinated with the City of Plano.

  • Custer Road permanent paving has begun in the right-hand lane at Plano Parkway and working north towards Dolphin Drive.
  • Cross streets and alleys between The Hope Center and Westridge Drive will have temporary closures while concrete cures, in sequence as crews move north.
  • Initial door hangers have been distributed to those planned to be impacted for trash pickup
  • Temporary signage notifying trash pickup instructions will also be placed in areas planned to be impacted, to move alongside construction
  • Permanent concrete pavement in all three northbound lanes along Custer Road is anticipated to be complete by the end of January 2027 but subject to weather delays.

Neighborhood Impacts

  • Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses. Contractor will be maintaining these areas until restoration efforts are complete.
  • Transition from the northern staging area to the southern staging area has been completed.
  • Activities at the northern staging area have been greatly reduced but will remain in place until the contractor returns to perform the final tie-in and restoration.
  • Use of the staging areas through project completion, which is currently targeted for May 1, 2027. Schedule is under review due to additional paving restoration beyond the contracted amount.

Timeline / What’s Next

November 2026

  • A shutdown of the City of Plano Custer Pump Station is anticipated for the final tie-in. Currently scheduled for the week of 11/30.
  • Disinfection testing of the entire waterline is anticipated in the week of 11/9.
  • Irrigation, sodding, and landscaping installation is anticipated to commence the week of 11/2.

Later Phases (Date TBD)

  • Permanent paving and restoration of vegetation.
  • Additional potholing will be performed along Carmel Drive, requiring street closure and detour (timing will be shared once scheduled).
  • A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle. Additionally, one lane closure will be required on Custer Road southbound outer lane (timing will be shared once scheduled).
  • 30-inch abandonment work will likely require additional traffic control phases along Custer Road (timing will be shared once phases are confirmed and scheduled).