NTMWD Project Update | April 10, 2026

Temporary transition from the northern staging area to the southern staging area complete

NTMWD Custer Road Water Main Replacement Project

Progress

  • 5,100 of 9,100 feet of pipeline have been installed.
  • Crews are continuing pipeline installation south towards Plano Parkway outside the northbound lane.
  • Hydrostatic testing of the waterline from City of Plano Custer Pump Station to Plano Parkway passed.
  • Permanent paving is being scheduled in coordination with trash pickup routes. Paving will begin at W 15th Street and Pitman Drive, and move south, currently scheduled for April 27.

Planned Traffic / Lane Impacts
Future traffic and/or lane impacts will continue to be coordinated with the City of Plano.

Neighborhood Impacts

  • Cross streets and alleys between Westridge Drive and Westlake Drive will have temporary closures from 9 a.m. to 4 p.m., in sequence as crews move southward for permanent paving.
  • Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses.
  • Transition from the northern staging area to the southern staging area has been completed.
  • Activities at the northern staging area will be reduced until the contractor comes back to perform tie-in and restoration, but may resume if inclement weather causes issues with access at the southern staging yard.
  • Use of the staging areas is to last until project completion, which is currently targeted for October 26, 2026

Timeline / What’s Next
April-May 2026

  • Atmos Energy initial phase of work is complete in the area, but will return after waterline installation is complete for permanent relocation of the gas line.

August 2026

  • Anticipated shutdown of the City of Plano Custer Pump Station for final tie-in.

Later Phases (Date TBD)

  • Testing/disinfection, permanent paving, and restoration of vegetation.
  • Additional potholing will be performed along Carmel Drive requiring a street closure and a detour (timing will be shared once scheduled)
  • A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle (timing will be shared once scheduled).