NTMWD Custer Road Water Main Replacement Project
NTMWD Project Update | February 13, 2026
Traffic shifts continue through early March
Progress
- 4,300 of 9,100 feet of pipeline have been installed.
- Air relief valve work between Westridge Drive and Grandview Drive is complete. Permanent paving has been restored.
Planned Traffic / Lane Impacts
During the planned closures, two-way traffic will be shifted to the southbound lanes. Northbound lanes will reopen once work is complete.
- Feb. 11 – Mar. 6: Custer Road (northbound lanes) closed between Glencliff Drive and Carmel Drive
- Final timeframes to be confirmed and shared by City of Plano.
Neighborhood Impacts
- Cross streets and alleys between Westridge Drive and Westlake Drive will have temporary closures from 9 a.m. to 4 p.m., in sequence as crews move south.
- Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses.
Timeline / What’s Next
February-March 2026
- Crews will install air relief valves in the Custer Road median (within the closure areas).
- Atmos Energy initial phase of work is complete in the area, but will return after waterline installation is complete for permanent relocation of the gas line.
- Permanent paving is scheduled to begin at W 15th Street and Pitman Drive.
- Crews will continue to install pipeline south towards Plano Parkway in the outside northbound lane of Custer Road.
May 2026
- Anticipated shutdown of the City of Plano Custer Pump Station.
Later Phases (Date TBD)
- Testing/disinfection, permanent paving, and restoration of vegetation.
- A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle (timing will be shared once scheduled).
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Contact Us
Email projects@ntmwd.com