NTMWD Custer Road Water Main Replacement Project
NTMWD Project Update | February 27, 2026
Temporary lane closure coming in mid-March on Pitman Drive
Progress
- 4,550 of 9,100 feet of pipeline have been installed.
- Air relief valve work between Glencliff Drive and Carmel Drive is complete. Permanent paving restoration in this area is scheduled for the end of this month.
Planned Traffic / Lane Impacts
During the planned closures, two-way traffic will be shifted to the southbound lanes. Northbound lanes will reopen once work is complete.
- Feb. 27 – Mar. 6: Custer Road (northbound lanes) closed between Glencliff Drive and Carmel Drive
- Final timeframes to be confirmed and shared by City of Plano.
Neighborhood Impacts
- Cross streets and alleys between Westridge Drive and Westlake Drive will have temporary closures from 9 a.m. to 4 p.m., in sequence as crews move south.
- Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses.
- A temporary closure on the southbound lane on Pitman Drive is expected to occur near the alley south of Shadow Trail the week of March 16 – March 20.
Timeline / What’s Next
March-April 2026
- Atmos Energy initial phase of work is complete in the area. Atmos will return after waterline installation is complete for permanent relocation of the gas line.
- Contractor anticipates testing the waterline from Pitman Drive and W 15th Street to just south of Westlake Drive and Custer Road the week of Mar. 16 – Mar. 20.
- Permanent paving will be scheduled to begin at W 15th Street and Pitman Drive after completion of the waterline testing.
- Crews will continue to install pipeline south towards Plano Parkway outside the northbound lane.
May 2026
- Anticipated shutdown of the City of Plano Custer Pump Station.
Later Phases (Date TBD)
- Testing/disinfection, permanent paving, and restoration of vegetation.
- A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle (timing will be shared once scheduled).