Progress
- 4,900 of 9,100 feet of pipeline have been installed.
- Additional crews have joined the construction of the water pipeline to help accelerate production.
Planned Traffic / Lane Impacts
- Future traffic and/or lane impacts will continue to be coordinated with the City of Plano.
Neighborhood Impacts
- Cross streets and alleys between Westridge Drive and Westlake Drive will have temporary closures from 9 a.m. to 4 p.m., in sequence as crews move southward.
- Temporary asphalt or steel plates will be used to reopen streets/alleys as work progresses.
- Transition from the northern staging area to the southern staging area will occur over the next two weeks.
- Activities at the northern staging area will be reduced until the contractor comes back to perform tie-in and restoration but may resume if inclement weather causes issues with access at the southern staging yard.
- Use of the staging areas is to last until project completion, which is currently targeted for October 26, 2026
Timeline / What’s Next
March-April 2026
- • Contractor will be testing the waterline from Pitman Drive and W 15th Street to just south of Westlake Drive and Custer Road the week of Mar. 23 – Apr 2.
- Permanent paving will be scheduled to begin at W 15th Street and Pitman Drive after completion of the waterline testing.
- Crews will continue to install pipeline south towards Plano Parkway outside the northbound lane.
May 2026
- Anticipated shutdown of the City of Plano Custer Pump Station
- Atmos Energy initial phase of work is complete in the area. Atmos will return after waterline installation is complete for permanent relocation of the gas line.
Later Phases (Date TBD)
- Testing/disinfection, permanent paving, and restoration of vegetation.
- Additional potholing will be performed along Carmel Drive requiring a street closure and a detour (timing will be shared once scheduled).
- A future phase will require closure of Carmel Drive between Custer Road and Delmonte Circle (timing will be shared once scheduled).