NTMWD Project Update | October 3, 2025
NTMWD Custer Road Water Main Replacement Project

NTMWD Project Update | October 3, 2025

Update from the Project Team

Project Status

  • The contractor has completed pipeline and temporary paving installation along Pitman Drive and Dolphin Drive near Custer Parkway.
  • Construction of the pipeline continues to progress; 1500 feet out of 9100 total feet of pipeline have been installed.
  • Tunneling for the pipeline is complete near Wilson Middle School. The contractor will be threading pipe through the tunnel soon.

Upcoming Activities (Oct. 6-13)

  • Excavation will be needed on Dolphin Drive to allow for the installation of water line appurtenances and manholes.
  • The pipeline crew will continue installation along Custer Parkway from Dolphin Drive to Carmel Drive.
  • Carmel Drive will be closed until Oct. 20 to facilitate pipeline construction.
  • Additional work will be performed in the median of Custer Drive north of Glencliff Drive for installation of vent piping, an air release valve and manhole.**

Future Activities

  • Temporary street closures will be necessary at Westridge Drive, Northcrest Drive, Westlake Drive and Dolphin Street.
  • An existing wastewater line will be replaced at Pitman Drive and Gardengrove Court.
  • Additional tunnelling will be needed under 15th Street at Pitman Drive to complete the pipeline’s connection to Plano’s Delivery Point.
  • Other work to finalize construction of the pipeline will include testing, paving and restoration of vegetation.