June 1 renovation updates
We continue to make progress on renovation work
Here’s the latest on what’s happening behind the scenes:
Men’s Locker Room: New sewer lines have been installed and concrete has been poured. Construction of above-ground plumbing and walls is now underway.
Women’s Locker Room: Sewer line installation is complete, with half of the concrete poured. Some walls and above-ground plumbing are also being built.
Family Changing Room: Plumbing has been stubbed up and is awaiting inspection before backfilling and concrete pouring can proceed.
Indoor Slide: Rebar installation is in progress for the new indoor slide stairs.
Outdoor Areas: New shade fabric has been installed to improve comfort and aesthetics around the facility.