2025-2028 Neighborhood Drainage and Sewer System Repair Contract
Week of 2/16/2026
Progress made on Ludlow St Swale Improvements.
This week, Gorham Sand & Gravel continued work on the Ludlow St Swale Improvements. They installed the first of two new stormwater inlet structures and the swale/underdrain work is approximately 90% complete. A second crew also capped the 12" diameter storm drain pipe being abandoned as part of this work. This coming week, GSG is expected to complete the swale/underdrain, install the second stormwater inlet structure, finish abandoning the old storm drain pipe, and begin constructing the new gravel carriage road to the swale.