2025-2028 Neighborhood Drainage and Sewer System Repair Contract
Week of 3/2/2026
Progress made on Ludlow St Swale Improvements.
This week, Gorham Sand & Gravel completed constructing the new gravel carriage road to the swale for access/maintenance. They also began to restore their laydown area. Early next week, the crew is expected to complete restoration of the laydown area and demobilize from the site. Upon completion of this scope of work, the crew will be mobilizing to the 236 Ludlow St Sewer Cross-Connection Correction site.