William St Sewer Manhole Scope Completed.

2025-2028 Neighborhood Drainage and Sewer System Repair Contract

This Week, GSG installed a new sewer manhole in the intersection of William St and Oakdale St. Next week, GSG is expected to mobilize to Canco Rd on Wednesday 6/17 to complete the Canco Rd Storm Drain Repair. Canco Rd will be closed to through traffic from Read St to Washington Ave on Thursday 6/18. Traffic flow from Washington Ave to Read St will be maintained at all times. The work is expected to be completed within about 3-5 days. Please see the construction notice, press release, and construction plan included under "Supporting Documents".