City of Portland, Maine
Hersey Street Sewer Separation Project

Hersey Street Sewer Separation Project

Overview

Ensuring the resilience and sustainability of Portland’s infrastructure is a top priority, and upcoming improvements on Hersey Street reflect this commitment. This essential project will separate stormwater from the sanitary sewer system, significantly mitigating combined sewer overflows (CSOs) into Back Cove. By reducing untreated sewage and stormwater discharge during heavy rainfall, we are not only protecting the health of Casco Bay but also advancing our broader efforts to enhance water quality and strengthen the integrity of Portland’s utilities. This phased project will also include the replacement of aging drinking water mains in partnership with the Portland Water District, ensuring long-term reliability for residents.

City staff understand the vital importance of working with the community throughout this process, as major public works projects can have localized impacts. While carefully designed to minimize disruption, construction will bring necessary changes to sections of Clifton, Hersey, and Ocean Avenue. Residents’ voices are instrumental in shaping how we manage construction timelines, ensure safety, and coordinate neighborhood access. We invite you to share your insights, concerns, and suggestions as we undertake this critical endeavor to improve our shared infrastructure and safeguard Portland’s natural resources for generations to come.

Base Bid Phase 1: Storm Drain/Sewer/Water within Hersey Street

  1. 3,300 linear feet of new gravity storm drain and sanitary sewer pipe
  2. 1,500 linear feet water main replacement
  3. The installation 4 new tree filters to provide stormwater quality treatment for the new storm drain system. This Green Infrastructure is being implemented to remove pollutants found in urban stormwater such as sediment, metals, hydrocarbons and excess nutrients before it discharges into Back Cove.
  4. Installation of bituminous sidewalk along northerly side of Hersey Street
  5. Repair of loam and seed at disturbed areas, and restoration of driveways affected by project
  6. Pavement restoration within Hersey Street
  7. New concrete sidewalk along the east side of Clifton Street
  8. Installation of 3 new speed tables on Hersey to reduce traffic speeds.

Base Bid Phase 2: Storm Drain/Sewer/Water within Ocean Avenue

  1. 1,000 linear feet of new gravity storm drain and sanitary sewer pipe
  2. 1,200 linear feet water main replacement
  3. Pavement restoration within Ocean Ave

Project Coordinators

  • City of Portland – Water Resources
  • Portland Water District
  • Design Engineer – Sebago Technics, Inc.
  • Owner’s Project Representative – Sebago Technics, Inc.
  • Construction Contractor – TBD

Weekly Construction Hours

  • Monday – Friday 7:00 AM – 7:00 PM
  • June 1 to August 31 7:00 AM – 8:00 PM
MAP

Opportunities to Engage

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Nathaniel Smith
City of Portland Water Resources

Project Phases

Design Phase 1
March 2025 - April 2025
Design Phase 2
August 2021 - February 2025
Bidding Phase
February 2025 - March 2025

Project Updates

Important Dates

4
Dec 2024

Neighborhood Meeting

Contact Us