2025-2028 Neighborhood Drainage and Sewer System Repair Contract

Week of 1/19/2026

Progress made on Ludlow St, Beaumont St, and Ballpark Dr scopes of work.

On Monday 1/19/2026, GSG mobilized to the Ludlow St Swale Improvement work zone in the Evergreen Cemetery. Throughout the week, GSG worked on clearing vegetation and trees marked for removal from the proposed swale limits. Additional tree removal work will likely be completed by T.W. Enterprises this coming week. Drainage work is expected to begin the following week.

On Tuesday 1/20/2026, GSG mobilized to the Beaumont St Inlet Improvements site and began work. Installation of the new 24" storm drain, flared end inlet, and riprap apron were completed on Wednesday 1/21/2026. The crew will return to this site at a later date to loam and seed the disturbed area.

GSG mobilized their equipment to the Ballpark Dr Outfall Repair site on the afternoon of Wednesday 1/21/2026 and began prepping the site for work. On Thursday 1/22/2026, they worked on removing woody vegetation/stumps from the work zone and filled the eroded drainage channel to prepare for the drainage work. This work will carry over into the coming week.

Completed inlet improvement work on Beaumont St