2025-2028 Neighborhood Drainage and Sewer System Repair Contract

Week of 2/2/2026

Progress made on Ludlow St and Ballpark Dr scopes of work.

On Monday 2/2/2026, Gorham Sand & Gravel finished installing erosion and sedimentation control measures at the Ballpark Dr Outfall Repair site. GSG has demobilized from the site and will return at a later date to complete any outstanding surface restoration work.

Over the course of the week, GSG began work on the Ludlow St Swale Improvements. A larger excavator and front end loader were mobilized to the work zone for installation of the riprap swale and underdrain pipe. This work will be ongoing in the coming week.

GSG beginning swale improvement work behind Ludlow St on the Evergreen Cemetery property.