Visit City of Portland, Maine Homepage
Week of 1/26/2026
Project

Week of 1/26/2026

Progress made on Ludlow St and Ballpark Dr scopes of work.

2025-2028 Neighborhood Drainage and Sewer System Repair Contract

On Thursday 1/29/2026, Gorham Sand & Gravel's tree cutter, T.W. Enterprises completed the tree removal work for the Ludlow St Swale Improvements. GSG will be mobilizing a larger excavator to the site this coming week to begin the drainage work.

Over the course of the week, GSG worked on installing the new drain manhole, extended storm drain outfall pipe, and riprap apron off of Ballpark Dr. The new pipe was backfilled on Thursday 1/29/2026 and the crew will be returning to the site this coming Monday to finish installing erosion and sedimentation control measures.

Operator spreading loam over new storm drain outfall

Stay Informed

Get notified on upcoming engagements and the latest project related news.