2025-2028 Neighborhood Drainage and Sewer System Repair Contract

Week of 1/12/2026

Project layout/flagging completed for Ludlow St Swale Improvements.

This week, Gorham Sand & Gravel (GSG) completed flagging their limits of work on the Evergreen Cemetery property and reviewed it with the City so that the necessary clearing and tree cutting can be completed ahead of the swale improvement work.

Looking Ahead:

  • GSG is expected to mobilize to the Beaumont St Inlet Improvement site this coming week on Monday January 19th.
  • Work on the Evergreen Cemetery property for the Ludlow St Swale Improvements will also begin on Monday January 19th.
  • As work progresses at Beaumont St, GSG will be mobilizing to Ballpark Dr to begin the outfall repair work, likely Tuesday January 20th or Wednesday January 21st.
Proposed contractor access route through Evergreen Cemetery