Visit City of Portland, Maine Homepage
Week of 6/15/2026
Project

Week of 6/15/2026

Progress made on Ludlow St punch list items.

2025-2028 Neighborhood Drainage and Sewer System Repair Contract

This week, GSG began completing punch list items associated with the Ludlow St Swale work. Pending weather and crew availability, GSG is expected to mobilize to Canco Rd to complete the Canco Rd Storm Drain Repair on Monday 6/22. Canco Rd will be closed to through traffic from Read St to Washington Ave on Wednesday 6/24. Traffic flow from Washington Ave to Read St will be maintained at all times. The work is expected to be completed within about 3-5 days. Please see the construction plan included under "Supporting Documents".

Stay Informed

Stay in the loop with all the latest updates on upcoming engagements and project news by signing up for notifications.