Dougherty Field Skatepark Expansion Project
The concrete and features work is complete and the skatepark now is "soft"ly open for general use. Please stay off the soil slope areas as we are trying our best to get gass seed established, and please keep litter and debris out of the seeded areas.
The Portland Skate park expansion is Portland Parks’ top Capital Improvement Project (C.I.P) priority for 2022 and 2023 construction. We are pleased to update skatepark visitors that final plans are under review with the planning department, and construction is tentatively planned for early April, 2023. We've leveraged over $40,000 in-kind donations to increase our square footage more than originally planned. Recent project funding request was for $235,000, to add to the existing $103,470 in private donations, and $70,000 in previous CIP funding allocations. Full project funding (funding donations and city CIP funding) is $408,470. Estimated project value will be nearly $450,000. Thank you to everyone involved!
To get the project there, special mention goes out to all of our skaters and families who have gotten pledges and donations from friends, relatives and neighbors as part of the Skate-a-Thon and summer and winter Rail Jam events. A lot of that money was raised $5 and $10 at a time. Huge thanks also goes to skaters Jack Kyle and Max Press who have connected local foundations to this effort that have contributed $85,000 towards this project. And the Long family (of the former Long's Board Shop) played a key role in building interest in this project and hosting some of our early events.
All of the private financial support raised for this project is deposited in a City fund for the exclusive purpose of the skatepark expansion project. You can keep tabs on the fund-raising by clicking here and also sign up to raise funds yourself. Moving forward, this project remains a priority for our Department-- and any funds raised moving forward will get us that much closer to our project funding goal.
Stay Informed
Get notified on upcoming engagements and the latest project related news.

Project Updates
July update - Concrete and feature work substantially complete
Skate-o-rama for Portland and friends
June 12th Work progress report
Finishing up transition features, flatwork ahead!
Dougherty Field Skatepark Concrete work week of May 22
Shotcrete a'com'n
Dougherty Field Skatepark Construction Underway
Work has begun!
Skatepark Expansion - Public Comment Design Revisions
Closing in on Final Design for Expansion
Skatepark Expansion - Public Design Meeting - October 19th, 6pm
Come join to hear about design parameters and preliminary concept work on Oct. 19th at 6pm
March 21st ,2022 City Council Meeting Approves CIP funding reuqest!
$235,000 in funding approved
Important Dates
CIP announcement date April 2022
Dates subject to change, but council approved funding requests for this project at their March 21st meeting. See the funding items at the provided link. https://portlandme.civicclerk.com/Web/Player.aspx?id=3400&key=-1&mod=-1&mk=-1&nov=0
RFP timeline / process April / May
Dates subject to change.
Construction Document Development and Permitting
Dates subject to change
Construction mobilization
Preparation of the work area starts getting underway! Materials, fencing, and other parts of the construction effort will start to arrive at the end of March and early April!
Construction begins!
Work starts in preparing the site for new expansion areas. Construction is anticipated to last through May, and, weather / conditions permitting, should conclude by mid June.
Concrete work set to start
Shotcrete work will begin on park features the week of May 22nd!