Visit City of Portland, Maine Homepage
Week of 2/23/2026
Project

Week of 2/23/2026

Progress made on Ludlow St Swale Improvements.

2025-2028 Neighborhood Drainage and Sewer System Repair Contract

This week, Gorham Sand & Gravel continued work on the Ludlow St Swale Improvements. They finished abandoning the old 12" storm drain pipe, completed construction of the underdrained swale (approximately 410' long), installed the second new stormwater inlet structure, and began constructing the new gravel carriage road to the swale for access/maintenance. Next week, the crew is expected to complete the carriage road, restore their laydown area, and demobilize from the site.

Ludlow St Swale

Stay Informed

Get notified on upcoming engagements and the latest project related news.