What's new about the Wasena Bridge Replacement Project?

Next week, on Monday, July 22, Archer Western has scheduled the next major concrete pour for Pier 2 footing and Pier 1 Column.

Here's what you need to know:
• Early Arrival: Crews will start arriving on site around 2 AM.
• Equipment and Deliveries: A concrete pump truck will arrive around 3 AM, followed by concrete delivery trucks.
• Concrete Pour: The concrete pour is scheduled to begin at 4 AM.

Due to the early arrival of trucks and equipment, there may be some intermittent noise from air brakes and backing alarms. We will make every effort to minimize disruptions.

Why Are We Starting Early?
The high temperatures we are currently experiencing cause the concrete to set too quickly. Starting early allows us to avoid high daytime temperatures and continue to keep the Wasena Bridge Replacement Project on schedule.