Washington Park Pool
Washington Park Pool Construction Update
We have exciting updates on the new Washington Park Pool.
Pool Construction:
* National Pools successfully cast the pool's concrete bottom and sides.
* Concrete perimiter will be poured in upcoming weeks.
**Pool House: **
* National Pools installed 75% of the masonry blocks for the main structure.
* In the coming weeks, the roof outline will take shape as the final masonry blocks are installed and steel trusses are placed.
The materials used for the pool and pool house were chosen to create a safe, long-lasting facility for the community.