Timeline

Work completed

May 2025 - May 2025
Work on the Kingswood Active Travel Improvements are completed

Construction begins

June 2024 to May 2026
Work is due to started in June 2024 on the first phase of improvements to make it easier for people to walk and cycle in and around Kingswood.

Public consultation

11 November 2023 - 23 December 2023
Capture feedback on the proposed improvements for people walking, using a wheelchair or cycling in and around Kingswood.

Submit final proposals to project sponsors

Early 2024 - Early 2024
We will consider feedback from the consultation and update our proposals where appropriate before submitting final plans to our funders.

News

13 items

Kingswood active travel improvements completed

Thank you to residents, visitors and commuters for your patience while we completed improvements across Kingswood.You can now enjoy wider shared-use paths, safer crossings and improved surfaces across

Posted:
View Update

Works to start on and around Cecil Road

Work is progressing well on the Kingswood Active Travel works. We are writing to you to inform you of the next phase of work, resurfacing on Cecil Road and South Road.  Closure details Blackhorse Road

Posted:
View Update

Works due to start on South Road

We’re pleased to confirm that the Kingswood Active Travel Improvements project is progressing on schedule. The next phase of works will begin on South Road, between Cecil Road and West Street, from 9

Posted:
View Update

Next phase of work to start on Blackhorse Road

Work is progressing well on the Kingswood Active Travel works. We are on track with our works on the current phase to improve the footways on Cecil Road.  The next phase of works will be on Blackhorse

Posted:
View Update

Next phase to start January 2026

Following the completion of improvements on the eastern footways of Cecil Road, Kingswood, all traffic management equipment has been removed onsite to allow the easy flow of traffic. Works in Kingswoo

Posted:
View Update
Halls Road with new parallel crossing near the junction with Cecil Road

Works completed on Halls Road

We’re delighted to announce the completion of improvement works on Halls Road in Kingswood. The project has delivered a brand-new parallel crossing, upgraded pavements, and resurfaced sections of the

Posted:
View Update

Next phase of works on Cecil Road

We are continuing our programme of improvements for walking and cycling around Kingswood as part of an Active Travel England project. The current road works on Halls Road are due to complete by 21 Nov

Posted:
View Update

Delay to Halls Road works

The installation of a new parallel crossing on Halls Road is taking longer than anticipated. To help keep things moving and reduce disruption, we changed how we work to make sure traffic can still flo

Posted:
View Update
Work on Cecil Road showing pavement widening and resurfacing

Next phase of improvements on Halls Road

We are moving onto the next phase of works in Kingswood to make travel safer and more accessible. Work is currently underway on Cecil Road, between Moravian Road and Halls Road, where we are widening

Posted:
View Update

Cecil Road improvements start

We are due to start making improvements to walking and cycling routes in Kingswood, and from 4 August work will begin on Cecil Road. The first week from 4 to 10 August there will be no road closure as

Posted:
View Update
Newly installed tactile paving on Pillingers Road, Kingswood

Walking route improvements

Over the summer we focused on improvements to walking routes between Staple Hill and Kingswood, installing a number of new pedestrian crossing, and widening pavements.Work has completed on: Page

Posted:
View Update

Construction to begin in June

Work is due to start on Monday 10 June on the first phase of improvements to make it easier for people to walk and cycle in and around Kingswood. The work will focus on the roads listed below and

Posted:
View Update

Consultation results published

The project team is grateful to the local people who shared their views via the engagement work completed from November until December 2023 on proposed pedestrian and cycling improvements in and aroun

Posted:
View Update

Meet the team

South Gloucestershire Council
South Gloucestershire Council

South Gloucestershire Council is responsible for running this consultation, analysing its results and presenting them to stakeholders and the public.

Read South Gloucestershire Council privacy policy

Contact us

If you have questions relating to this consultation survey, you should contact us by email. If you want to talk to someone about issues related to roads, you should call our customer services team.

Call 01454 868004