100 Percent Design Documents

The Town of Southern Pines and Kimley Horn have released the 100% design plans for the Knoll Road Multi-Modal Trail


May 22, 2026


Knoll Road Multi-modal Trail description text.

Knoll Road Multi-modal Trail

The Town of Southern Pines has released the 100% design plans for the Knoll Road Multi-Modal Trail project, managed by our contractor Kimley-Horn. The plans are available at:

https://sopinesnc.info/KnollRoad100PercentPlans

  • The Knoll Road Multi-Use Path Project will construct a new multi-use path along Knoll Road from Midland Road (NC 2) to Airport Road (SR 1843).
  • The project includes grading, paving, and drainage improvements along approximately 1.5 miles of corridor.
  • The new multi-use path is designed to improve pedestrian connectivity, accessibility, and safety along the Knoll Road corridor.
  • Fred Smith Company has been selected as the contractor for the project.
  • A Notice to Proceed will be issued on June 1, 2026.
  • Construction staking and utility marking activities are expected to begin the week of May 25, 2026.
  • Town staff and the contractor are scheduled to conduct a project walkthrough on June 2, 2026.
  • Active construction is expected to begin within approximately two weeks following the project walkthrough.
  • The total contract duration is 270 calendar days.
  • Construction completion is anticipated in early Spring 2027, with a current estimated completion date of February 26, 2027.
  • Residents may see temporary lane closures, equipment activity, and construction personnel in the area throughout the duration of the project.
  • Updates regarding traffic impacts, construction schedules, and project milestones will be posted to this page as work progresses.