Dear property owners, business managers, and other stakeholders:
The Borough of State College is writing to provide you with the latest updates regarding Phase 2A of the Calder Way Improvement Project.
This week, the contractor continued installation of the water main along Hetzel Street. This work will continue next week.
Early next week, Columbia Gas will work on lines in the intersection of Calder Way and Hetzel Street. Once Columbia Gas is finished, installation of storm structures will resume.
Vehicular traffic along Hetzel Street from Beaver Avenue to College Avenue is closed. Deliveries along Hetzel Street can be made along Calder Way. Delivery drivers can enter from South Garner Street, deliver to the designated location, and exit via South Garner Street. The contractor will assist delivery drivers.
Please remember that projects of this nature are fluid and often change, and they can be impacted by inclement weather. You will be updated in a timely manner about these changes as they are received.
The Borough emphasizes that primary communications will be sent via email through the Calder Way Communications list. Weekly updates will be provided on Thursday afternoons, and there will be times you receive more than one update per week as conditions change.
For updates and information about Phase 2A of the Calder Way Improvement Project. You can contact me directly at Tklinefelter@statecollegepa.us or (814) 680-4468. For assistance after hours, please contact Centre County’s non-emergency line at 1-800-479-0050.
If you know of anyone who would like to receive the updates, please instruct them to contact me and ask to be added to the Calder Way Improvement Project updates.