Lake Howard Gravity Sewer and AC Force Main Replacement

With positive growth and development continuing in Winter Haven, The Winter Haven Water Department strives to prioritize water and sewer infrastructure projects that capture multiple community benefits.

The City of Winter Haven Water Department has contracted with Cathcart Construction Company to preform the following improvements to the sanitary sewer system within the vicinity of Lake Howard.

The Lake Howard Gravity Sewer and AC Force Main Replacement Project is a two part project. The gravity sewer main portion of this project will occur on the East Side of Lake Howard while a section of AC Sewer Force Main will be replaced on the West Side.

*Maps of road closures for this project can be found in the supporting documents section of this page.


Updates to this project will be ongoing, stay informed!





Phase 2 Map of Road Closures

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"The Lake Howard Gravity and AC Force Main Sewer Project provides upgrades to the infrastructure creating multiple benefits for the community. "
Steve Rheiner
Project Manager

Project Timeline

Bidding and Award
Fall 2023 to Summer 2024
Construction
September 2023 - May 2024
South Lake Howard Dr Closed from Ave D SW to Ave B SW
Beginning October 30, 2023 - Approximately 3 Months

Project Updates

Important Dates

25
Sep 2023

Public Meeting

The City of Winter Haven Water Department will be hosting an open house style public meeting on September 25th,2023. Please feel free to stop in between the hours of 5:00 p.m. and 7:00 p.m. at 401 6th Street SW Winter Haven, Fl. 33880 to discuss project specifics with the project management team.