Warwick Way Town Centre Highways Scheme

Warwick Way Town Centre Highways Scheme

Construction of the Warwick Way Town Centre Highways Scheme is now complete.

The scheme has introduced wider footways, improved pedestrian facilities, new planting, and improved cycling provision throughout the area.

The Council will be undertaking post-implementation monitoring over the coming months to assess how the completed scheme is operating.

Further information on the scheme can be found here.

About the project

Email

News

35 items

Tachbrook and Churton Street Construction Updates - 19.06.2026

All the footway works are now complete. Due to urgent gas works along Tachbrook Street the remaining carriageway resurfacing works have had to be delayed.  The resurfacing works are currently pla

Posted:
View Update
pvopcdndmipcfbyereel.jpg

Tachbrook Street Construction Updates - 05.06.2026

Phase 4 & 5 Tachbrook Street Construction works have been completed at junction of Tachbrook Street and Charlwood Street.  An extension in paving along Tachbrook St near the junction wit

Posted:
View Update
fftbh1rpqilou6ku9cey.jpg

Tachbrook Street Construction Updates - 22.05.2026

Phase 4 & 5 Tachbrook Street Construction works are on-going at the junction of Tachbrook Street and Charlwood Street.  Footway works outside Cask Public House on the northern arm of Cha

Posted:
View Update
pwy6q7u1zep7ww0o7u97.jpg

Tachbrook Street Construction Updates - 08.05.2026

Phase 4 & 5 Tachbrook Street Construction works are on-going at the junction of Tachbrook Street and Charlwood Street.  Footway extension works are largely complete on the north-western

Posted:
View Update
oge76yujgjkl3prdmhon.jpg

Churton Street Construction Updates - 24.04.2026

Phase 2 Churton Street (between Belgrave Road and Charlwood Place)The outstanding paving and drainage work in this section have been completed, allowing for the road closure at the junction with Belgr

Posted:
View Update
iancf2pzo08oyiv87ej0.jpg

Churton Street Construction Updates - 10.04.2026

Phase 2 (between Belgrave Road and Charlwood Place)Construction is on-going along Churton Street between Tachbrook Street and Belgrave Road. During the works an existing underground carriageway void w

Posted:
View Update
u8ubrftkvufkanaakdwu.jpg

Churton Street Construction Updates - 27.03.2026

Phase 2 Churton Street (between Belgrave Road and Charlwood Place)Construction is on-going along Churton Street between Charlwood Place and Belgrave Road.  During the works an existing underground car

Posted:
View Update
Photo of a construction site

Churton Street Construction Updates - 13.03.2026

Phase 2 (between Belgrave Road and Charlwood Place)Construction is on-going along Churton Street between Tachbrook Street and Belgrave Road.  During the works an existing underground carriageway void

Posted:
View Update
vmrxpv2suctc5tpoxedd.jpg

Warwick Way Construction Updates - 27.02.2026

Phase 1 Churton Street (between Charlwood Place and Churton Place)All footway works are complete along Churton Street between Charlwood Place and Churton Place.Phase 2 (between Belgrave Road

Posted:
View Update
enfjhndbtgs5zlqs7knp.jpg

Warwick Way Construction Updates - 13.02.2026

Phase 1 Churton Street (between Charlwood Place and Churton Place)All footway works are complete along Churton Street between Charlwood Place and Churton Place, except for the loading bay immediately

Posted:
View Update
j8rlldmae129qazfvvnw.jpg

Warwick Way Construction Updates - 30.01.2026

Phase 1 Churton Street (between Charlwood Place and Churton Place)All footway works are complete along Churton Street between Charlwood Place and Churton Place, except for the loading bay immediately

Posted:
View Update
tgvv8h29hpmleez8vykn.jpg

Warwick Way Construction Updates - 16.01.2026

Phase 1 Churton Street (between Charlwood Place and Churton Place)All footway works are complete along Churton Street between Charlwood Place and Churton Place, except for the loading bay immediately

Posted:
View Update
qpoxblk8xnjqx0rpmiqk.jpg

Warwick Way Construction Updates - 19.12.2025

Phase 1 Churton Street (between Tachbrook Street and Charlwood Place)All footway works are complete along Churton Place between Tachbrook Street and Charlwood Place, except for the loading bay immedia

Posted:
View Update
i0hxxv9d5azc8f4eftnt.jpg

Warwick Way Construction Updates - 05.12.2025

Phase 1 Churton Street (between Tachbrook Street and Charlwood Place)All footway works are complete along northwest side of Churton Place between Tachbrook Street and Charlwood Place.  On the sou

Posted:
View Update
fwbttpvifxoua51aip3a.jpg

Warwick Way Construction Updates - 21.11.2025

Phase 1-5 Warwick Way & Phase 6 Upper Tachbrook Street (between Longmoore Street and Warwick Way)Works are complete for phases 1 to 6 along Warwick Way & Upper Tachbrook Street.  However tree

Posted:
View Update
otkpduqjguaymnwqf8xt.jpg

Warwick Way Construction Updates - 07.11.2025

Phase 1-5 Warwick Way Works are complete for Warwick Way phases 1 to 5.  However remaining works include tree pit reinstatement on Denbeigh Street and tree planting along Warwick Way, which will be co

Posted:
View Update
v7ugvfy0ske50pf0dp22.jpg

Warwick Way Construction Updates - 24.10.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 including the loading bay outside Tesco.  Phase 2 Denbigh StreetThe works on Denbigh Street

Posted:
View Update
qei2fqm8xmd830opuldu.jpg

Warwick Way Construction Updates - 10.10.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the loading bay outside Tesco, works for which are currently underway with kerb

Posted:
View Update
vp501scfvaoqsqs5ruas.jpg

Warwick Way Construction Updates - 26.09.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
cbog00zp0esuuzzq6ben.jpg

Warwick Way construction updates - 12.09.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
Works progressing on Churton Street

Warwick Way construction updates - 04.09.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update

Warwick Way construction updates – 15.08.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
dakbatjboxi8a462arac.jpg

Warwick Way Construction Updates - 01/08/25

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
fqsk5d5peuw4ru1mwapk.jpg

Warwick Way Construction Updates - 22/07/25

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered kerbs to the loading bay outside Tesco.

Posted:
View Update
l5fs84qggryai5o4xuab.jpg

Warwick Way Construction Updates - 04/07/25

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
rhqwyu7pjdrwliytgonk.jpg

Warwick Way Construction Updates - 06.06.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update

Warwick Way construction updates – 30.05.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
hj0e2i9xfvnwhxerjfct.jpg

Warwick Way Construction Updates – 09.05.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
aqtjh3barard8j4lw0qr.png

Warwick Way Construction Updates - 28.04.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. &nbsp

Posted:
View Update
w8zrhs4msgia463j2cqv.jpg

Warwick Way Construction Updates - 14.04.2025

Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road) Works are have largely been completed.  As previously advised, a delay to a materials delivery has resulted in a change to the way

Posted:
View Update
bwalcoypa3n554t2aaop.jpg

Warwick Way Construction Updates - 28.03.2025

Warwick Way Phase 1 (between Upper Tachbrook Street and Wilton Road)Works so far:Deep drainage works to install connections to the sewer have been completed.   Widening on both sides of Warwick Way ha

Posted:
View Update
nmghmksn6p8wahcbsmkd.jpg

Warwick Way Construction Updates - 14.03/2025

Warwick Way Phase 1 (between Upper Tachbrook Street and Wilton Road)Works so far:Deep drainage works to install connections to the sewer have been completed and works have been progressing on the wide

Posted:
View Update
taiv659qeul1spnfwq3f.jpg

Warwick Way Construction Update 28th February 2025

Warwick Way Phase 1 (between Upper Tachbrook Street and Wilton Road)Works so far: Deep drainage works to install connections to the sewer have been completed and works are progressing to construc

Posted:
View Update
tio27mezcbwj5hpdux8t.jpg

Warwick Way Construction Updates – 14.02.2025

Warwick Way Phase 1 (between Upper Tachbrook Street and Wilton Road)Works so far:Drainage:All three deep drainage connections have now been successfully completed with the final hole back filled this

Posted:
View Update

Construction on Warwick Way commenced on 6th January 2025

Construction on Warwick Way has started and is expected to continue until October 2025.Works so far:Works on Warwick Way (Phase 1) began as planned on Monday 6th January and Warwick Way is currently c

Posted:
View Update

Meet the team

Westminster City Council
Westminster City Council

This scheme is fully funded by Westminster City Council and the City Highways Public Realm team is overseeing the delivery of the project.

Read Westminster City Council privacy policy

FM Conway
FM Conway

FM Conway is the principal designer and contractor for this scheme. If you have any queries, please email to warwick-churtonwestminster@fmconway.co.uk

Read FM Conway privacy policy