Updates
- May 2026 Construction Update
- Phase 2 - Right-of-way acquisition has started for the second phase of the project.
- Contractor continues with water meter and fire hydrant relocations on Riney Road
- Construction Progress
- Phase 6 - Contractor to start work at US77 & Bonnie Brae
- May 2026 Update and Lookahead
- Detour/Closure Update! April 2026
- April 2026 Construction Update - 3
- News Update - April
- Construction on Park Improvements Begins April 27, 2026
- Asphalt Paving Operations Begin
- Contractor concentrating on Sawcutting and Utility Relocations along Riney Road
- April 2026 Construction Update - 2
- April 2026 Construction Update
- April Update
- April Update
- Construction Progress
- March 2026 Update and Lookahead
- News Feed - March
- Phase 6 - Temporarily and intermittently closure of Conquest Drive for limeing operations
- Bonnie Brae Phase 6 - Updated Road Closure Notice
- Westgate Dr Phase 1 March Update
- March Update
- March Update and Lookahead
- March 2026 Construction Update
- Phase 2 - Right-of-way Acquisition is on hold.
- Phase 6 - Contractor to lower existing waterline for clearance of new infrastructure
- Construction Start Date selected by Contractor to be March 16, 2026
- Virtual Community Meeting scheduled for March 2026
- Pre-Construction Meeting held at the Development Services Center
- Construction Contract Awarded to Quality Excavation, LLC.
- Construction Progress
- Close-out phase
- Construction Progress
- February 2026 Construction Update - 2
- Feedback on the Southeast Denton Overlay Districts
- Project Update - February 2026
- February Update
- February Update
- February Update and Lookahead
- February 2026 Construction Update
- News Feed - February
- News Feed - February
- January 2026 Construction Update - 2
- Project Update - January 2026
- January Update and Lookahead
- Phase 6 - Road Closure Update - Bonnie Brae from US77 to Riney Road
- January 2026 Construction Update
- January Update (So Long 2025, Hello 2026)
- January Update (Happy New Year)
- December Update and Lookahead
- Recommended Code Updates for Townhomes and ADUs
- Phase 1 December Update
- December 2025 Construction Update
- Progress Update
- Traffic Update - Bridge Material Deliveries!
- 12/2025 Progress Update
- Project Update
- Project Update
- Project Update
- Active Construction
- PUB & Council Set
- Moving to PUB & Council
- Bidding Opening this Month
- Moving Forward towards Solicitation
- Update on Easements
- Easement Updates
- Easements Still needed
- Movement on Easements
- Awaiting Easements
- Offer Letters Have Been Sent
- ROW negotiations still in progress
- Right of Way Acquisition
- Planning and Design Complete!
- Easement Acquisition
- Design Review Update
- Start of Construction
- Bidding
- Going Out to Bid
- Nearing Bid Time
- About to Bid Project
- Easements & Design
- Between 90% & 100% Design
- 90% Design Completed
- 60% Design Completed
- Phase 1 November Update
- Phase 1 October Update
- Phase 1 September Update
- Phase 1 August Update
- Phase 1 July Update
- Phase 2 - Right-of-way Acquisition is on hold
- Phase 2 - Project Limit Reminder
- Phase 1 April Update
- Phase 2 - Right-of-way Acquisition
- New project limits - Westgate Drive Phase 2 Improvement Project
- The East/West Westgate Drive will be first to be constructed.
- Right-of-way Acquisition continues
- City has purchased 0.3 mitigation credit.
- United States Army Corps of Engineers issues Permit Authorization Letter
- 100% Pre-Final Plan Set being reviewed by City.
- Consultant Engineer plans to submit 100% Plan Set in late June 2024
- Virtual Community Meeting
- The 90% Plan Set review continues at the City!
- 90% Plan Set submitted to the City.
- Halff Associates continues to work on permanent and temporary construction easement documents.
- ROW acquisitions to begin soon.
- Completing plan revisions
- 60 percent plan set is complete!
- 30 Percent Plan Schematic is complete.
- Design Survey is Complete.
- Westgate Drive
- Choosing the Consultant Engineer for Design
- Westgate Project Scope Update
- Westgate Improvements Project Update
- Thursday, May 20 Virtual Community Meeting Replay
- Virtual Community Meeting Thursday, May 20
- Westgate Improvements Project Update
- News Feed - September
- News Feed - April
- News Feed - March
- News Feed - February
- News Feed - January
- News Feed - November
- News Feed - September
- News Feed - July
- News Feed - May
- News Feed - April
- News Feed - March
- News Feed - February
- News Feed - January
- News Feed - December
- News Feed - November
- News Feed - October
- News Feed - September
- News Feed - August
- News Feed - July
- News Feed - June
- News Feed- May
- News Feed - April
- News Feed - March
- News Feed - February
- News Feed - January
- Competitive Seals Bid are being graded by City Staff
- Bidding Phase for the Project
- The City is reviewing the 90% complete Project Manual
- The Project Manual has been submitted to the City for its review.
- 100% Plan Set submitted to the City.
- Right-of-way Acquisition Process Complete!
- 90% Plan Set Review Completed by the City
- Phase 1 Environmental Site Assessment are being conducted.
- Appraisal Reports Completed.
- Appraisal Reports near Completion
- Consultant Engineer continues to work on Plan Set!
- Right of Way Acquisition Process has started!
- The 60% Plan Set is being reviewed by both internal and external stakeholders!
- 60% Plan Set submitted to the City.
- Binkley & Barfield is working on the project schematic plans.
- Design Contract Awarded
- News Feed - September
- News Feed - April
- News Feed - March
- News Feed - February
- News Feed - January
- News Feed - December
- News Feed - November
- News Feed - October
- News Feed - September
- News Feed - August
- News Feed - July
- News Feed - June
- News Feed - May
- News Feed - April
- News Feed - March
- News Feed - February
- News Feed - January
- Dec. 15 Public Input Meeting
- November Update and Lookahead
- October Update & Lookahead
- September Update & Lookahead
- August Update & Lookahead
- July Update
- June Update
- May Update
- April Update
- March Update
- April 2025 Update
- March 2025 Update
- January 2025 Project Update
- November Update
- September Progress Update
- April Update
- January 2025
- November
- September update
- Project Update - September 2025
- Project Update - June 2025
- Project Update - April 2025
- Project Update - January 2025
- Project Update - November 2024
- Project Update - October 2024
- Project Update - September 2024
- Project Update - August 2024
- Project Update - July 2024
- Project Update - June 2024
- Project Update - April 2024
- Project Updates
- HILLTOP is RE-OPENED!!
- Falling for Fall on Hickory Creek
- Summer Fun on Hickory Creek Road
- REMINDER - TRAFFIC CHANGE to Hilltop Road
- Traffic Impact
- April 2025 Project Update
- March 2025 Project Update
- January 2025 Project Update
- November 2024 Project Update
- September Project Update
- August Project Update
- July Project Update
- Hickory Creek Road Phase 3 Project Update
- Monthly Project Update
- Monthly Project Update
- Monthly Project Update
- Monthly Project Update
- Monthly Project Update
- Project Update
- Project Update
- Hickory Creek Rd Project Video Update
- Project Update
- Project Status Update
- Hickory Creek RD Closure
- Closure Update
- Project Updates
- Project Update
- Utility Line Relocations
- Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting
- Hickory Creek 3 Visual Presentation
- Hickory Creek Road Phase 3 Virtual Community Meeting Replay
- Upcoming Virtual Community Meeting
- Construction Progress
- Construction Progress
- Construction Progress
- Design/Procurement Phase
- Design/Procurement Phase
- Design/Procurement Phase
- Design/Procurement Phase
- Design/Procurement Phase
- Design/Procurement Phase
- Design/Procurement Phase
- Design Phase
- Design Phase
- Design Phase
- Design Phase
- Design Phase
- Design Phase
- Schematic Design Phase
- September 2025 Project Update
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Progress
- Construction Phase
- Construction Phase
- Construction Phase
- Phase 6 - Construction activities continue between Conquest Drive and US77
- PHASE 3 - (Airport Road/FM 1515 to Roselawn) *WILLOWWOOD CLOSED until November 1.
- Phase 6 - Construction Activities between University Drive to Windsor Drive
- PHASE 3 (FM1515/Airport Rd to Roselawn) 9.10.2025 Bonnie Brae CLOSED between Willowwood & Parvin
- Phase 6 - Reeves Elementary School access along Riney Road
- PHASE 3 (FM1515/Airport Rd to Roselawn) FULL ROAD CLOSURE: AIRPORT ROAD, BONNIE BRAE at 35E - 7.30 through 8.18.2025
- PHASE 3 (Airport Rd/FM 1515 to Roselawn) PARVIN ROAD CLOSED 7.21 - 9.5.2025
- Phase 6 - Contractor continues to work on concrete pavement detour.
- Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae
- Phase 6 - Installation of 12-inch waterline for Reeves Elementary School
- PHASE 3 - FM1515/Airport Road to Roselawn
- Phase 6 - Full Notice to Proceed given to Tiseo Paving Company
- Partial Notice to Proceed issued to Tiseo Paving Company
- Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.)
- News Feed - January (Bonnie Brae Phase 5_ University - Scripture)
- News Feed - December (Bonnie Brae Phase 5_ University - Scripture)
- News Feed - November (Bonnie Brae Phase 5_ University - Scripture)
- Texas Department of Transportation reviews Bid Opening Documentation! (Phase 6)
- News Feed - October (Bonnie Brae Phase 5_ University - Scripture)
- Bid Results being analyzed for approval by Stakeholders (Phase 6)
- News Feed - September (Bonnie Brae Phase 5_ University - Scripture)
- The Pre-Bid Meeting is scheduled for August 8th! (Bonnie Brae Phase 6)
- News Feed - August (Bonnie Brae Phase 5 _University - Scripture)
- The Bidding Phase has arrived! (Bonnie Brae Phase 6)
- News Feed - July (Bonnie Brae Phase 5 _University - Scripture)
- Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6)
- News Feed - June (Bonnie Brae Phase 5 _University - Scripture)
- Contract Documents being finalized! (Bonnie Brae Phase 6)
- Revisions to the 100% Plan Set continues at TxDoT
- 100 Percent Plans submitted to TxDoT
- Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street)
- November 2025 Construction Update
- Project Update - June 2025
- Project Update - April 2025
- Project Update - February 2025
- Project Update - January 2025
- Project Update - November 2024
- Project Update - October 2024
- Project Update - September 2024
- Project Update - August 2024
- Project Update - July 2024
- Project Update - June 2024
- Project Update - April 2024
- Project Updates
- October 2025 Construction Update - 2
- October 2025 Construction Update
- September 2025 Construction Update - 2
- September 2025 Construction Update
- August 2025 Construction Update - 2
- August 2025 Construction Update
- 12/12/24 New Traffic Pattern - Avenue C Is Opening Up Today!
- 2024 11-18 UNT Area Update
- Look Ahead Near UNT
- 11/12/2024 Look Ahead Update
- Look-Ahead Update 8/24/24
- 6/28/24 Update and Lookahead
- 6/10/24 Update and Lookahead
- 6/4/24 Update and Lookahead
- Work Package #2 is starting SOON
- 5/12/24 Update and Lookahead
- Traffic Control Update - Crescent - Linden - Thomas
- 4/22/2024 Update and Lookahead
- 4/5/2024 Update & Lookahead
- 3/29/2024 Update
- 3/22/2024 Update
- February Update
- January Update
- December Update for Neighborhood 2 & 6
- November Update for Neighborhood 6
- September Update for Neighborhood 6
- Update for Neighborhood 6 Project
- Update for Neighborhood 6 Project
- Project Update for Neighborhood 6
- Neighborhood 6 Project Update
- 2019 Bond Neighborhood 6 Update
- September 2025 Update
- Missing Middle Housing Types in Denton
- Policy Support for Denton's Missing Middle Housing
- Bid Advertisement for Construction
- Construction Underway
- Evers Property Update (September 2025)
- Design Downtown Denton Plan Dashboard
- Starting Construction
- Grenada Trail Road Closure
- ALH Art Project by The Art Room
- Across the road, Ryan Rd. opened back up.
- Nearing Completion
- Foundational Choices Made
- Project Underway, Upcoming Road Closure
- The End of the Bypass Era
- Plant Back to 100%
- Project Update and Upcoming Plant Shut Down
- Electrical Pole Being Moved
- Status Update
- Continued Basin Rejuvenation
- Bypass and Vault Progress
- Old Wet Well Filled in
- 30 Percent Cost Model Delivery
- Submittals and Aerial Redesign
- Discussion with City Council Feb 4
- Progress Report - Basin Rehabilitation Underway
- Construction Update: Initial Demolition Steps Begin
- Construction Update: Progress Report
- Exciting News! Construction Has Commenced
- Key Milestones Approaching in CMAR Delivery
- Update: Construction Contractor Selected & Moving Forward!
- Contractor Selection Begins
- Project Status Update!
- Sedimentation Basins
- Lots of Work Underway
- Ongoing Collaboration
- Continued Teamwork
- Presenting to PUB and City Council
- Received construction permits for Denia
- Project Update
- 3 Week Look Ahead
- Getting Started
- Project Update
- Design Updates
- In Search of a Contractor
- Design Downtown Denton Plan
- Potholing Update
- Mobilization Begins
- Preconstruction Meeting
- Early Project Update
- Out to Bid
- How a Lift Station Works
- Benefits of Variable Frequency Drives (VFDs) over Switchgear
- Unlocking Efficiency and Sustainability in Wastewater Treatment
- Benefits of Gravity Sewer Mains over Force Mains
- How do we treat the raw water coming from Lake Ray Roberts?
- The Feedback Finale Update
- The Feedback Finale
- April Events Overview
- Did you miss the Public Meeting?
- Meeting Reminder!
- Quakertown Park Design Workshop
- Join us for our First Community Meeting!
- Your Voice Matters! Help Shape Our Inclusive Playground Project!
- Moving into "Phase 3: Act"
- Privet Removal at Villages of Carmel Park (Feb. 2024)
- November and Early December Events
- Workday December 9
- Progress
- TPWD Grant Awarded
- TPWD Grant Submission
- Master Plan Adopted
- Work day - December 3, 8am-3pm
- Privet Removal at Bowling Green Park - Beginning Dec. 2023
- Design Downtown Denton Visioning Workshop
- Trail Work to Restart After Summer Heat
- Quakertown Park Visioning Workshop
- Design Downtown Denton Launch and Events
- Advisory Group Meeting #1
- Trail Construction Continues
- Advisory Group Selected
- Project Kickoff Meeting and Site Visit
- Goals and Vision for the All-Inclusive Playground!
- Moving Forward: Denia Park's Next Steps - Seeking Council Approval for an Exciting Transformation
- Parks and Recreation Staff Visits Local Playgrounds
- Active Adult Center Fact Sheet
- Active Adult Center Project Presented to Bond Committee
- South Lakes Park Mountain Bike Trail Master Plan
- Trail Development Work Day - May 27
- Celebrating Lily Cantú
- Design Consultant Hired!
- Trail Development Kick-Off
- Grant Awarded!
- Project Initiation
- February 20 - Hybrid Public Input Meeting Recap
- Hybrid Community Meeting Scheduled! Join us on February 20.
- Funding Identified!
- Weather Conditions Delay
- Habitat Restoration in Action!
- Bowling Green Park
- Master Plan Adopted